Doe’s Report On The August Blackout

Secretary Abraham’s remarks on the release of the blackout report indicate some failure to meet reliability standards on the part of FirstEnergy, among other things: The Electric System Working Group found that the initial events that led to the cascading blackout occurred in Ohio. The blackout was initiated when three high-voltage transmission lines operated by …